1987
Feiling Electric Engineering Co., Ltd. was established.
1990
Feiling Electric Consulting Co., Ltd. was established.
1995
Completed several 69kV substation projects for Taiwan power company.
1997
The engineering department completed Taiwan power company 345kV substation project.
1999
ISO 9001 certification was obtained.
2003
Undertook Toshiba Plant Co.'s high-speed rail project in Taiwan, completing the electromechanical system package for eight substations along the line.
2008
Completed 345kV power facilities and equipment installation projects for Taiwan power company.
2014
Feiling Electric Vietnam Co., Ltd. was established, Feiling Group officially expanding into the international market. The company also began import/export trade business, acting as an agent for products and engaging in both domestic and international sale
2015
Miaoli Power Plant upgrade project: 345kV switchyard control, protection, auxiliary power equipment, and SCADA system installation.
2016
In response to business growth, Feiling Group was officially established.
2019
Offshore wind farm Phase 1 demonstration project.
2021
Taichung Power Plant 345kV (South) GIS update project.
2022
Changhua Southeast and Changhua Southwest offshore wind farm project land-based substation construction: 230kV & 161kV GIS equipment procurement and installation project.
2023
Fuxing Fangyuan Wind Farm 22.8kV cable package, Hitachi Taiwan Sustainable Energy Co., and Winbond Electronics Corporation 161kV GIS*5 electromechanical installation project.
2024
Yali Electric Co.'s Yunlin PS 23kV GIS procurement and replacement installation. Hwacheng Electric Co.'s Miaoli Power Plant upgrade project, fire pump room electrical equipment installation.
2025
Group headquarters, scheduled for completion in December 2025. – In Taichung City, Dadushan District.